Economic Justification for Sealcoating

Sealcoating will save real dollars as shown in the following tabulation. The cost Contact JDK Pavement - A Sealcoating Company, at 603.532.1100savings will be a substantial 65% if the pavement is maintained according toa schedule recommended by the manufacturer. Unsealed pavements will require repairs starting with the second year and a one(1) inch overlay every seven years. The damage to the unsealed pavement could be even more costly if the proper repair schedule is ignored.

YEAR OPERATIONS PERFORMED Sealed Sq. Meter UnSealed Sq. Meter
1994 Base Installations
2 Inches of Asphalt
Two (2) Coats of Sealer
$7.20
$6.60
.48
$7.20
$6.60
.00
1995 First Year Maintenance Coat
.00 .06
1996 Second Year Maintenance Coat
.00 .18
1997 Third Year Maintenance Coat
Two (2) Coats of Sealer
.24
.72
.36
.00
1998 Fourth Year Maintenance Coat
.00 .48
1999 Fifth Year Maintenance Coat
.00 .65
2000 Sixth Year Maintenance Coat
Two (2) Coats of Sealer
.84
$1.08
.00
2001 Seven Year Maintenance 1.5" Overlay
.00 $5.40
2002 Eight Year Maintenance Cost .00 .11
2003 Nine Year Maintenance Cost
Two (2) Coats of Sealer
.33
$1.44
.32
.00
2004 Tenth Year Maintenance Cost
.00 .54
2005 Eleventh Year Maintenance Cost
.00 .90
2006 Twelfth Year Maintenance Cost
Two (2) Coats of Sealer
.95
$1.80
$!1.21
.00
2007 Thirteenth Year Maintenance Cost
.00 $1.54
2008 Fourteenth Year Maintenance Cost
.00 $1.90
2009 Fifteenth Year Maintenance Cost
Two (2) Coats of Sealer
.00
$2.16
$10.80
.00
  Installation and Maintenance on Average Parking Lot Per Square Meter $23.84 $39.07
  On a 10,000 square meters asphalt pavement, the total estimated savings will amount to $152,000 over a 15 year period. Values in U.S. dollars.    